4 New Chip Projects Cleared: India’s 10-Project Pipeline, Real Timelines

Cabinet nods on Aug 12 expand the pipeline. Expect OSAT/ATMP to ship first; wafer-fab volumes follow as clusters harden.
By bataSutra Editorial · August 16, 2025
In this piece:
  • What just happened — four new approvals
  • Project map and types (fab vs. OSAT/ATMP vs. compound)
  • Realistic timelines & outputs (2025–27)
  • Why OSAT first — the operating logic
  • Milestones and risks for the next 12 months

The short

  • Four new projects cleared. Odisha (2), Andhra Pradesh, Punjab — taking sanctioned units to ~10.
  • Near-term output is packaging-heavy. ATMP/OSAT lines can ship within 12–18 months; fab ramps are multi-year.
  • Anchor nodes are in Gujarat and Assam. Micron ATMP, Kaynes OSAT, TSAT Assam lead 2025 shipments; Dholera fab ramps 2026–27.

Project map & types

Wafer Fabs

Mature nodes for auto/industrial at Dholera. Long lead Yield climb

OSAT / ATMP

Sanand, Assam hubs for assembly & test. Faster go-live Talent ramp

Compound Semis (SiC / 3DHI)

Odisha approvals add high-value packaging/SiC capacity. Power devices 3D glass

Policy & Incentives

Stacked central/state support, cluster infra, and supply-chain tie-ups. MoUs Utilities

Timelines & outputs

ProjectLocationTypeStatus / indicative timing
SiCSem (with Clas-SiC)Bhubaneswar, OdishaSiC / fab elementsCabinet-approved Aug 12; DPR & site prep next.
3D Glass SolutionsBhubaneswar, OdishaAdvanced packaging (3DHI)Cabinet-approved Aug 12; high-density packaging focus.
CDILMohali, PunjabAnalog/discrete + packagingCabinet-approved Aug 12; expansion/modernisation path.
ASIP TechnologiesAndhra PradeshSystem-in-Package (SiP)Cabinet-approved Aug 12; details with DPR.
Micron ATMPSanand, GujaratATMPOperational readiness 2025; DRAM/NAND packaging.
Tata–PSMCDholera, GujaratWafer fabMature nodes; ramp through 2026–27.
Tata TSATJagiroad, AssamOSATOperations commencing 2025; phased scale-up.
Kaynes SemiconSanand, GujaratOSATSamples around Sep 2025; commercial by Dec 2025.
CG Power–Renesas–StarsSanand, GujaratOSATPilot by mid-2026; mass production 2027.
Key: OSAT/ATMP = assembly & test; DPR = Detailed Project Report.

Why OSAT first?

  • Speed-to-market: Shorter tool lead times and fewer utility constraints than greenfield fabs.
  • Talent ramp: Builds technician/QA base that fabs later absorb.
  • FX resilience: Packaging in India reduces finished-chip import exposure ahead of local wafer output.

Milestones to watch

  • Kaynes Sanand: samples → customer quals → commercial ops.
  • Micron Sanand: cleanroom readiness and outbound logistics cadence.
  • Dholera fab: utilities uptime, tool-move timelines, specialty-chemical offtakes.
  • Odisha/AP/Punjab projects: DPRs, land allotments, incentive tie-ups.

Risks

  • Global tool bottlenecks elongating fab critical path.
  • Yield climb on initial nodes; vendor hand-holding needed.
  • Cycle sensitivity at OSATs (handset/server demand).